Inspired By Water.Property Improvement Project
As of September 2022, the Pelican Beach Resort has commenced a waterproofing project on its exterior. To minimize disruption to guests and owners, a detailed plan has been devised to concentrate work on designated sections of the building at a time. However, there may be brief closures of some condominium balconies, grounds, and facilities during the course of the work. We will continue to update this message as advances are made in the project.
March 20, 2023 Update: All balconies will be available for use during Spring Break! The contractor will remove all of their equipment from the Gulf side of the building (stacks -07 to -11) from March 10 to April 17, 2023. Rental guests will have full use of balconies during this time frame.
Expect waterproofing project work on the walkways side of the building (north elevation) from March 16 to approximately May 1. Work will include pressure-washing and the application of sealants and coatings. This work will present some inconveniences but owners and renters will always have access to unit doors. Noise during the next four weeks will mainly be related to the pressure-washing process. They expect there to be little noise from grinders and other equipment associated with surface preparation and concrete repairs.
Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. Please keep in mind that the condo building immediately west of us, Regency Towers, is doing waterproofing work, too, and generating noise from concrete repairs. Please advise your renters that we have no control over this noise.
Gulf Pool (new pool) deck will be closed from April 17 to approximately May 6 while balcony coatings are applied and other work is done. New hot tub may also be closed during this period.
IMPORTANT NOTE: Please keep in mind that schedules and work activities are subject to change with little or no notice depending on such factors as weather and equipment problems.
Open. Gulf Pool (new pool) deck will be closed from April 17 to approximately May 6 while balcony coatings are applied and other work is done. New hot tub may also be closed during this period.
Open
Open
Open
Open
Open. Fitness room has a new flooring along with new treadmills, ellipticals and a recumbent bike. Steam Room was completely remodeled with new tiles and door.
The swimming pool at our sister property, The Terrace, is open and available for use by Pelican renters. The pool is about a 5-minute walk from the Pelican main lobby.
The hot tub at our sister property, The Terrace, is open and available for use by Pelican renters. The hot tub is about a 5-minute walk from the Pelican main lobby.
Open
Open Daily from 7:00am to 4:00pm
Open Daily from 10:00am until ?
The waterproofing renovation only effects the exterior of the property. The renovation project affects all units at Pelican Beach Resort. If you are contemplating renting directly with an owner (Vrbo, etc.) or an off-site third-party management company, this schedule affects these units as well.
The following is an overview by condominium based on the unit number. Example: “Unit 701” is Floor 7, Unit Number (Stack) 01.
PELICAN BEACH SITE MAP
• Balcony furniture will be returned as soon as possible to balconies after the "Finishing" date shown for each numbered stack. It may take 1-4 days, or more, after the "Finishing" date for balcony furniture to be returned.
• If a balcony needs additional work, guests will NOT have access to the balcony and the balcony furniture for that unit will NOT be returned along with the furniture of other units in the same stack. It will be returned as soon as the engineers for the project tell us the balcony is ready for use.
• All dates in the schedule above are based on "perfect working conditions." This means that fog, high winds, rain and high humidity are likely to change these dates. Other factors may also affect the schedule.
Walkway: Completed/No Impact
Balcony: South faced balcony estimated renovation completion date: Mar. 6; Estimated balcony-use date: Mar. 6-10.
East faced balcony estimated completion date: Jan. 11; Estimated balcony-use date: Jan. 14.
Walkway: Completed/No Impact
Balcony: Estimated renovation completion date: Mar. 6; Estimated balcony-use date: Mar. 6-10.
Walkway: Completed/No Impact
Balcony: Estimated completion date: Mar. 9; Estimated balcony-use date: Mar. 9-13.
Walkway: Completed/No Impact
Balcony: Estimated completion date: Mar. 9; Estimated balcony-use date: Mar. 9-13.
Walkway: Completed/No Impact
Balcony: Estimated completion date: Mar. 10; Estimated balcony-use date: Mar. 10-14.
Walkway: Completed/No Impact
Balcony: Estimated completion date: Mar. 10; Estimated balcony-use date: Mar. 10-14.
Walkway: Completed
Balcony: Estimated completion date: To Be Determined; Estimated balcony-use date: Mar. 11 to late April or late May. Additional Note: The contractor plans to complete all concrete repairs and other “noisy” work between Jan. 18 and March 11. On or about March 11, they will remove all scaffolding and move to another part of the building to work. From March 11 to a date yet to be determined (after Spring Break, probably mid- or late April or early May), renters will be able to use the balconies. Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. The current plan is for balconies to be open for the Memorial Day weekend.
Walkway: Completed
Balcony: Estimated completion date: To Be Determined; Estimated balcony-use date: Mar. 11 to late April or late May. Additional Note: The contractor plans to complete all concrete repairs and other “noisy” work between Jan. 18 and March 11. On or about March 11, they will remove all scaffolding and move to another part of the building to work. From March 11 to a date yet to be determined (after Spring Break, probably mid- or late April or early May), renters will be able to use the balconies. Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. The current plan is for balconies to be open for the Memorial Day weekend.
Walkway: Completed
Balcony: Estimated completion date: To Be Determined; Estimated balcony-use date: Mar. 11 to late April or late May. Additional Note: The contractor plans to complete all concrete repairs and other “noisy” work between Jan. 18 and March 11. On or about March 11, they will remove all scaffolding and move to another part of the building to work. From March 11 to a date yet to be determined (after Spring Break, probably mid- or late April or early May), renters will be able to use the balconies. Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. The current plan is for balconies to be open for the Memorial Day weekend.
Walkway: Completed
Balcony: Estimated completion date: To Be Determined; Estimated balcony-use date: Mar. 11 to late April or late May. Additional Note: The contractor plans to complete all concrete repairs and other “noisy” work between Jan. 18 and March 11. On or about March 11, they will remove all scaffolding and move to another part of the building to work. From March 11 to a date yet to be determined (after Spring Break, probably mid- or late April or early May), renters will be able to use the balconies. Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. The current plan is for balconies to be open for the Memorial Day weekend.
Walkway: Completed
Balcony: Estimated completion date: To Be Determined; Estimated balcony-use date: Mar. 11 to late April or late May. Additional Note: The contractor plans to complete all concrete repairs and other “noisy” work between Jan. 18 and March 11. On or about March 11, they will remove all scaffolding and move to another part of the building to work. From March 11 to a date yet to be determined (after Spring Break, probably mid- or late April or early May), renters will be able to use the balconies. Work on the balconies of the -07 to -11 stacks will resume April 17 and be completed approximately May 6. Balconies of these stacks will be locked and furniture will be removed. Weather may cause changes in the schedule. Work will include the painting of railings on the lower floors and the application of coatings to the balcony/patio decks. The current plan is for balconies to be open for the Memorial Day weekend.
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units
Balcony: Estimated completion date: Jan. 13; Estimated balcony-use date: Jan. 17
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units
Balcony: Estimated completion date: Jan. 13; Estimated balcony-use date: Jan. 17
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units Balcony: Estimated completion date: Jan. 13; Estimated balcony-use date: Jan. 17
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units
Balcony: Estimated completion date: Jan. 22; Estimated balcony-use date: Jan. 25
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units
Balcony: Estimated completion date: Jan. 22; Estimated balcony-use date: Jan. 25
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units
Balcony: Estimated completion date: Jan. 21; Estimated balcony-use date: Jan. 24
Walkway: Outdoor walkways (streetside) work will take place Mar. 20-May 26. Guests will always have access to units.
Balcony: Estimated completion date: Jan. 23; Estimated balcony-use date: Jan. 26
Mar. 27-May 5: Elevator stack above Lobby. No direct impact on balconies.
Mar. 6-24 - West face of building work. No direct impact on balconies, except possibly noise and dust for -10 & -11 units Important note: Please keep in mind that rain, humidity, wind and cold temperatures may lead to changes in this schedule.
For Pelican Beach Management guests, we are the largest management company with vacation rentals at Pelican Beach. We have the inventory when available and the ability to move guests to less affected parts of Pelican Beach or to the Terrace at Pelican Beach. Thus, guests of Pelican Beach Management can continue to book with confidence that we will recommend and place guests in condominiums with the least impact to this project. Please call (888) 735-4226 for the best options available for your travel dates.
Please note, Pelican Beach Management has no control of the timetable and locations of work. That is within the control of the Pelican Beach Homeowners Association. Additionally, we do not have any control on Vrbo or other management company reservations. Guests will need to contact those parties for any advice or questions.